On a fixed-price contract, you carry 100% of material price risk. Tariffs, supply chain disruption, and market volatility can turn a profitable job into a loss overnight. This tool generates a ready-to-paste escalation clause that protects your margin — calibrated to your contract.
Price adjustment kicks in only after material costs rise above a set % (e.g., 5%). Most common. Balanced.
Any material price increase is passed through. Favors contractor. Owners rarely accept without a cap.
Escalation applies only to delays beyond the original schedule. Protects against owner-caused delays.
Copy this into your contract or add as a rider. Have your attorney review before signing.
If the owner pushes back on the threshold: Offer a higher threshold (7-10%) to show good faith. You're still protected against major spikes while the owner feels protected from minor fluctuations.
If the owner won't accept any-increase: They're right. Switch to threshold — it's more balanced and more likely to be accepted.
If the owner wants a lower cap: A 10% cap is reasonable for short projects. For projects over 6 months, push for 15-20% because material prices can move significantly over longer periods.
Always document baseline prices: Save supplier quotes or invoices at the time of bid. The clause is useless if you can't prove the original price. The index reference in your clause provides the objective benchmark.
Research from ConsensusDocs, Bracewell LLP, and construction industry publications consistently shows that material price escalation is the #1 contract risk for contractors in 2026. Tariffs, supply chain disruption, and market volatility can turn a profitable fixed-price contract into a loss — and most small contractors don't know how to write an escalation clause, or think they're "not big enough" to include one.
That's wrong. Any contractor on a fixed-price contract should have an escalation clause. This tool makes it easy.
Get a free review from Corbelworks
Tell us what's costing you — we'll look at the numbers and reply within 1 business day. No pitch, no commitment.